11.04.26 Conservation Commission Public Hearing
words this meeting uses bylaw · public comment · public hearing — the glossary says what they mean
tap to load the tape · nothing plays until you dothe same, as a table
| time | kind | the moment |
|---|---|---|
| 0:11 | decision | Great. Thank you. Okay. Good evening. In accordance with the Massachusetts Wetlands Protection Act, MGLC 131, section… |
| 10:59 | pushback | So, I couldn't figure out what's what. |
| 17:43 | decision | provided with 30 foot turning radiuses um and a 60-oot turning circle. And currently we have exactly um 60 ft nose… |
| 20:51 | decision | Okay. Thank you. So with that I'd entertain a motion to continue the hearing. |
| 21:17 | decision | Oh, I'm sorry. Okay. Thank you. That carries 5 nothing. Okay. Thank you. |
| 22:47 | decision | Uh Massport is charged with the development, operation, and maintenance of its properties. As a general rule… |
| 29:47 | decision | Uh so again work was combined to the existing developed pier um and resource area values and functions were not… |
| 33:27 | pushback | I think so. I I mean I think if somebody's conducting the inspection and has concerns about something that might be… |
| 38:58 | decision | Okay. So with that, I would entertain a motion to close the hearing and issue an order conditions with a special… |
| 39:28 | decision | And I vote I that carries for uh 5 nothing. Thank you. |
| 57:19 | pushback | partially a cash flow issue. So, the larger renovation will be a larger pot of money. Um and we will be able to do all… |
| 59:35 | decision | Okay. Yep. Okay. Great. So, with that, I would uh entertain a motion to close a hearing and issue an order of… |
| 1:00:12 | decision | So moved. |
| 1:16:56 | pushback | While we were out there, you could also really see uh the waves and tidal action going into this area that is not… |
| 1:17:44 | pushback | Uh we to clarify would be requesting that the commission um ratify the emergency certification if they find it… |
| 1:19:02 | pushback | Um when we were sort of talking through the requirements for the emergency certification, uh one of the things that we… |
Cut from the analyzer’s scored moments — a measurement, not a choice made for you. Open a reel and press make this reel yours to re-cut it; tick any moment or transcript line below to cut your own.
The Boston Conservation Commission met on November 4th, 2026 [0:19] to review environmental permitting and resource area projects. The commission voted to continue the hearing on resurfacing and stormwater improvements [20:51], approved an order of conditions for an after-the-fact security fence at 88 Black Falcon Avenue [39:00], and voted to approve an order of conditions for temporary structural repairs at the Jamaica Pond Boat House [59:37]. Commissioners also voted to grant certificates of compliance for projects at the Matahunts property [1:04:04], Turtle Pond Parkway [1:05:54], and 59 GV Street [1:08:28]. Following staff briefings on administrative items and emergency work [1:09:09], the commission voted to ratify an emergency certification regarding a seawall collapse at Boston Shipyard [1:22:46] before approving meeting minutes and adjourning [1:24:08].
What it means: The Boston Conservation Commission [0:49] held a virtual public hearing chaired by Michael Parker [1:20] to evaluate wetland and resource area impacts across multiple city projects. The commission voted to continue the hearing regarding a U.S. Postal Service vehicle maintenance facility paving project [2:29], [21:00]. The commission also approved an after-the-fact notice of intent for pier repairs by Heidelberg Materials subject to special staff consultation conditions [22:09], [39:00], and approved temporary structural support work at the Jamaica Pond Boat House with special preconstruction reporting conditions [3:59], [59:35]. Additionally, the commission approved multiple certificates of compliance [1:04:06], [1:06:11], [1:08:26], reviewed administrative approvals [1:09:01], ratified an emergency certification for collapsed seawall repairs at the Boston Shipyard and Marina [1:17:13], [1:22:40], and accepted previous meeting minutes [1:24:10].
Who moved it: The meeting was led by Chair Michael Parker [1:20], alongside participating commissioners identified as Commissioner Sullivan [1:38], Commissioner Len [1:40], Commissioner Essargi [1:43], and Commissioner Herpst [1:49]. Staff updates and technical comments were presented by commission staff member Elena [3:47], [1:08:54]. Applicants and representatives delivering project presentations included Brett Alen [2:54] and Christy Filippo [3:02] for the Postal Service project, David [21:48] and Michael [35:10] for Heidelberg Materials, and Brandon Conungle [40:19] alongside Kevin Bogle [40:29] for the Jamaica Pond project. Unnamed commissioners moved and seconded the various formal votes throughout the meeting [20:54, 39:14, 59:58, 01:04:21, 01:06:25, 01:08:41, 01:23:14, 01:24:17], as the transcript does not explicitly name the individual mover for every motion.
What to watch: For the continued Postal Service application, the applicant was directed to return with a Licensed Site Professional or detailed responses regarding site contamination numbers, groundwater infiltration, and parking space environmental trade-offs [15:07], [18:22]. Heidelberg Materials must coordinate with commission staff to establish regular monitoring and written reporting on the structural condition of its pier [32:40], [39:00]. The Jamaica Pond Boat House team must provide preconstruction plans detailing construction methods and notify staff if pond water levels are lowered for the work [55:05], [1:00:02]. Finally, the operators of the Boston Shipyard and Marina must provide a visual plan or sketch of their ongoing emergency seawwall work and follow up with a full notice of intent filing for long-term repairs [1:17:26], [1:22:50].
Scored, not chosen for you — the salience bar is a measurement, and every moment is a receipt into the transcript below. With JavaScript on, tick moments to compose a reel — and tick moments on other meetings too; a reel can span the record.
→ the publish kit for this meeting — the clips worth cutting and draft copy, for a producer.
Counted, not modeled — each lens is a word list; drift compares the first half to the second.
the same, as a table
| word | mentions |
|---|---|
| commissioner | 64 |
| work | 58 |
| site | 43 |
| area | 40 |
| boston | 36 |
| water | 36 |
| conditions | 30 |
| project | 30 |
| slide | 26 |
| commission | 25 |
| sullivan | 25 |
| number | 25 |
| file | 24 |
| building | 24 |
| maintenance | 22 |
| within | 22 |
| buffer | 20 |
| mean | 19 |
| maybe | 18 |
| foot | 18 |
| plan | 18 |
| order | 17 |
| impacts | 17 |
| storm | 16 |
| parking | 16 |
| nothing | 16 |
| good | 15 |
| staff | 15 |
| concrete | 15 |
| able | 15 |
| sure | 15 |
| issue | 15 |
| hearing | 14 |
| already | 14 |
| something | 14 |
| part | 14 |
| temporary | 14 |
| pond | 14 |
| emergency | 14 |
| great | 13 |
| land | 13 |
| resource | 13 |
| last | 13 |
| massport | 13 |
| len | 12 |
| street | 12 |
| subject | 12 |
| back | 12 |
| comments | 12 |
| property | 12 |
| needed | 12 |
| areas | 12 |
| repairs | 12 |
| fence | 12 |
| pier | 12 |
| certificate | 12 |
| elena | 11 |
| plans | 11 |
| believe | 11 |
| little | 11 |
“commissioner” came up 64 times. Sized by how often; civic stopwords out. With JavaScript off, a word opens the tape at its first mention.
0:02 And everyone is in now.
0:03 Great. Thank you. Okay. Good evening. In
0:05 accordance with the Massachusetts
0:06 Wetlands Protection Act, MGLC 131,
0:09 section 40 in the Boston Wetlands
0:11 Ordinance, Boston City Code Ordinances,
0:13 Chapter 7-1.4, Four, the Boston
0:16 Conservation Commission will hold a
0:17 virtual public hearing this evening on
0:19 November 4th, 2026 to review the
0:21 following projects to determine what
0:24 conditions, if any, the commission will
0:25 impose in order to protect the interests
0:27 of the public and private water supply:
0:29 groundwater, prevention of pollution,
0:30 flood control, prevention of storm
0:32 damage, protection of fisheries and land
0:34 containing shellfish, and protection of
0:36 wildlife habitat. Uh this evening's
0:39 hearings will be followed by our regular
0:40 meeting and in accordance with chapter
0:42 107 of the acts of 2022. We are
0:45 conducting this meeting online to ensure
0:47 public access to the deliberations of
0:49 the conservation commission. The public
0:50 may access this call through telephone
0:52 and video conferencing. Additionally,
0:54 the meeting is being recorded. If you do
0:56 not wish to be recorded, please turn off
0:57 your video. Members of the public may
1:00 have an opportunity to ask questions and
1:01 provide public comment on applications
1:03 and discussions. To do so, please raise
1:06 your hand or type in the chat in the
1:07 application via the Zoom meeting
1:08 platform. If you're calling in and
1:10 cannot use the platform, you can raise
1:12 your hand by pressing star9 and star six
1:14 to unmute yourself or send questions to
1:17 staff via email at cc@boston.gov.
1:20 For the record, I am Michael Parker,
1:21 chair of the commission. Could staff
1:22 please identify themselves?
1:24 Elena with the environment department.
1:27 Dee Hernandez with the environment
1:29 department.
1:31 Lucina Dawala with the environment
1:33 department.
1:33 Great. Thank you. Uh, okay. I'll call
1:36 the role of, uh, commissioners present.
1:38 Uh, Commissioner Sullivan,
1:39 John Sullivan,
1:40 Commissioner Len,
1:42 Amy Len,
1:43 uh, Commissioner Essiasi, has he made it
1:46 yet?
1:46 He has not joined us yet.
1:47 Okay. He'll be here later, apparently.
1:49 Uh, okay. Commissioner Herpst.
1:52 Okay. Okay. First, uh, item on the
1:55 agenda tonight actually has been
1:57 continued to the December 9th, 2026
1:59 hearing. its notice of intent for D file
2:01 number 006 2135 in Boston file number
2:04 2026-032
2:07 from AECOM on behalf of uh DCR uh for
2:11 the proposed inkind replacement of a
2:13 water line and placement of concrete
2:15 mattresses from Hull to George's Island.
2:17 Uh second item on the agenda uh is
2:20 notice of intent for D file number
2:22 0062149
2:24 Boston file number 2026-043
2:27 from GM2 on behalf of the United States
2:29 Postal Service for the proposed pavement
2:31 resurfacing and storm water improvements
2:33 at the Boston Vehicle Maintenance
2:34 Facility located at 131A Street South
2:37 Boston uh waterfront uh resource area
2:41 land subject to coastal storm flowage.
2:43 Um this meeting uh or this hearing has
2:46 been continued from the October 21st,
2:48 2026 hearing. So uh who's here on behalf
2:51 of the proponent?
2:54 Good evening. My name is Brett Alen of
2:56 GM2 Associates.
2:58 Okay,
3:00 anyone else?
3:02 We also have Christy Filippo from MMT.
3:09 Okay. So, um we had a few uh as we said,
3:13 we already uh had one hearing on this.
3:16 So, we have uh this hearing we had a few
3:19 things that we were asking for. Uh I
3:22 remember um the uh turning radiuses in
3:25 the parking lot uh because we're trying
3:27 to see if uh we could cut back on some
3:29 of the imperous surface. Uh we're asking
3:32 about uh the storm water infiltration
3:35 system and uh evidence from the LSP that
3:39 um storm water infiltration was uh not a
3:42 good idea at this site because of the uh
3:44 soils underneath the parking lot. Um
3:47 Ellena, is there anything else here?
3:50 Uh the only other thing that I had
3:52 included were some additional questions
3:53 from Commissioner Sullivan. Uh they're
3:55 noted in the staff comments and the
3:56 project team had uh provided answers to
3:59 those questions. Uh I haven't been able
4:02 to check with Commissioner Sullivan to
4:03 see if those um satisfied the the
4:06 inquiries.
4:08 Okay. So, uh Brett, why don't we go over
4:10 the uh issues that were residual from
4:12 the last hearing? We don't have to go
4:14 over the whole presentation again.
4:16 Uh it's actually a new presentation
4:17 addressing those comments specifically.
4:19 Perfect.
4:20 So, it might be uh something we can flip
4:22 through quickly. So, if we go to the
4:24 next slide, um it does indicate, as you
4:27 mentioned a couple times, October 21st
4:29 was our last presentation to the board.
4:31 Um we did submit on October 30th a LSP
4:35 letter addressing stormwater
4:36 infiltration um by the project's LSP,
4:39 which is WSP. Um a vehicle turning
4:42 figure was also provided as well as
4:44 revised project plans.
4:47 Next slide, if you could.
4:52 So project plans were updated based on
4:55 some of the exterior surrounding
4:56 vegetation uh generally along the abuing
5:00 roadways uh from Medallion A to the
5:02 west, Hall Road to the east, and some
5:05 isolated vegetated trees at the project
5:08 limits. There's really nothing on the
5:09 interior. However, we did provide uh
5:12 those notations on the project plans as
5:14 a good effort to ensure those are
5:16 protected. Um we can go to the next
5:18 slide.
5:22 This is actually a similar slide to the
5:24 last and it comes into play with some of
5:26 the vehicle turning and green space
5:28 considerations. Uh as a reminder, a lot
5:30 of the vehicles are double parked under
5:32 today's condition. This is just a
5:34 snapshot from Google Maps 2026 showing
5:37 the personal vehicles are double parked.
5:39 The operations vehicles on the right
5:41 figure are double parked, maybe even
5:43 triple parked. Um and then we have
5:45 carrier vehicles that are parking in
5:46 unstriped territory. Um partially
5:50 because of sight constraints as well as
5:51 some of the operations for sequencing to
5:53 get the personal vehicles in while the
5:56 operation vehicles are uh shifted about
6:00 we can move to the next if you don't
6:02 mind.
6:04 So we did provide vehicle turning tests
6:07 for that southern parking area. Um, this
6:10 area is stored with 11 ton box trucks.
6:13 And a consideration is that USPS
6:16 standard, which is in that lower left uh
6:19 clip, actually requires the parking
6:21 stalls to be 35 ft in length. We have a
6:24 30 foot as an exemption to the USPS
6:27 federal uh or national criteria for the
6:30 design to maximize parking on site. So,
6:33 if we did have 35 foot long stalls, we
6:37 would inherently be losing some parking
6:39 on site. Um, additionally, this is a
6:42 select few uh kind of randomized parking
6:46 considerations for the vehicles to turn
6:48 and get into those stalls.
6:52 We can move on.
6:55 Uh, we also had some comments regarding
6:57 proprietary devices and as mentioned,
7:00 Commissioner Sullivan had some secondary
7:02 comments received over the past couple
7:03 weeks that I'm hoping to go over now.
7:06 Um, so there are 10 proprietary devices
7:09 uh generally for pre-treatment or a a
7:12 form of pre-treatment for sediment
7:15 removal and solids removal. Um these are
7:19 storm scepters shown on the project
7:21 drawings and generally they are
7:23 positioned offline of the main trunk
7:25 line. The main trunk line receives storm
7:27 water from the surrounding streets and
7:30 goes into a 30 in uh two 30-inch
7:33 conveyance as well as a 42in conveyance
7:35 on site. So these proprietary carry
7:37 devices are selected offline and subject
7:41 to only the storm water received within
7:43 the project limits. Um the intent is
7:46 that we are not providing any adverse
7:48 effects to the larger storm water
7:51 conveyance throughout the property. Um
7:53 we also had some comments on the hoods
7:55 and bioskirt locations. Those are shown
7:57 on the drawings as well as um detailed
8:00 and again those are provided offline of
8:03 the main conveyance structures. Um we
8:06 can go to the next slide if you could.
8:09 And some of the last comments we had, we
8:11 had two regarding uh roof conveyance as
8:15 well as the existing sumps. Um so this
8:18 is an example um kind of two birds with
8:21 one stone situation. Uh so shown in the
8:24 red uh layout there is a blow up showing
8:28 the rims inverts and sumps were obtained
8:32 um in the survey as shown on the
8:35 drawings as well as the 10-in uh pipe
8:40 roof leader connecting into the larger
8:41 conveyance on site. Um, one comment that
8:45 did come up uh outside of the meeting
8:47 was that regarding the existing storm
8:49 water structures, uh, those are to
8:51 remain. So, they're going to be cleaned.
8:53 The pipe on site is going to be cleaned,
8:56 structures cleaned, and then there's
8:57 going to be some modifications to the
8:59 new pipe connections, uh, with the
9:01 proprietary devices. Um, [clears throat]
9:04 I believe that,
9:06 um, was both the comments addressed from
9:08 the last meeting as well as some that we
9:10 received in the last couple days, but
9:11 I'd like to open it for any comments or
9:13 concerns, questions, etc.
9:15 Sure. Thank you. So, I did read the
9:18 letter uh, from your LSP. Uh, so that
9:21 answered my questions. I don't think you
9:23 went into it uh, in the presentation. Do
9:25 you want to give a brief overview of um,
9:28 of that issue?
9:30 Uh, I I'll only say that the LSP
9:34 identified that any infiltration would
9:36 be um against the regulations for
9:39 stormwater infiltration due to adverse
9:42 underlying conditions. Um, I defer to
9:45 them on what the underlying conditions
9:47 are specifically. I think they mentioned
9:48 it in the letter as well as some
9:50 history.
9:51 Yep, understood. Um, yeah, there are two
9:53 RTNs there. Okay. Um, Elellanena, what
9:56 do you have on this?
9:58 I didn't have anything further on this.
9:59 Um, I would defer to Commissioner
10:01 Sullivan on the follow-up questions for
10:03 the um, issues that are noted in the
10:04 staff comments.
10:05 Okay. So, we'll go to Commissioner
10:07 Sullivan on the um, questions he had and
10:09 uh, Commissioner Essargia, let the
10:11 record uh, reflect that he's joined us
10:13 and he had the questions about the uh,
10:16 truck turning radius. So, I'll uh, leave
10:18 that to his in his good hands.
10:20 Commissioner Sullivan.
10:22 Yeah. Yeah. So, I reviewed um what the
10:25 answers were when I had asked the
10:26 question were there 4oot sumps? Uh the
10:29 response was why don't you read the
10:30 plans? Um which I did and there's a
10:32 whole bunch of them with 2 and 1/2t
10:34 sumps. So you know thank god I could
10:36 read the light shaded gray uh which I
10:39 did. There are also some catch bases in
10:41 Medallion Avenue which um I I get from
10:44 the proponent that it's like well that's
10:46 not my problem. Well Medallion Avenue in
10:48 that location is a private way. When you
10:51 are but the private way you own half the
10:53 street so it is your problem. But
10:55 there's no data on those catch bases.
10:57 So, I couldn't figure out what's what.
10:59 The proprietary stuff, I don't disagree
11:01 with you. Um, those those are all fine.
11:04 Um, I was trying to say, is there a
11:06 better way to space them out, have less
11:08 of them, maybe a little larger? You
11:10 could save yourself money because in
11:13 [clears throat] the order conditions,
11:14 you'll be required to give us updates
11:16 when you clean them and all that, but
11:17 should you choose to use 11, uh, you
11:20 know, good luck to you. And the
11:21 bioskirts, I found those interesting. um
11:25 you're putting them on a bunch of the
11:26 basins and those will be required in the
11:29 order of conditions I'm assuming under
11:31 the maintenance plan that you check them
11:33 for the first year or two and then once
11:35 a year change them so we can just modify
11:38 that you do have extraneous water
11:40 entering your site uh owned by um I
11:44 think Massport Authority owns some I
11:46 know that Mass DOT has water running
11:48 through your site with a particle
11:49 separator sitting in your site I was
11:52 surprised that you and pull all that
11:54 out. I I see what you're saying is,
11:57 well, they're not mine, so I don't have
11:58 to worry about them despite the fact I
12:00 connect to them. So, overall, I was
12:03 disappointed also in the AUL call. I try
12:06 to check that out, the RTN numbers. I It
12:10 looked to me like the AUL had been
12:12 lifted um at some point a couple years
12:15 ago, and that the AUL wasn't covering
12:17 the entire site. Not saying that you
12:20 couldn't do partial infiltration some
12:22 spot uh and not in others. Um what we'll
12:26 do is we'll be following up with that
12:27 later with the professional LSP to see
12:30 what what was really going on um as part
12:33 of the water sewer washing out because
12:35 you discharge into our pipes and we can
12:37 control what comes into our pipes. So
12:40 overall, um, very disappointed in the
12:42 professionalism of what the way I was
12:44 responded to, but we will continue the
12:47 hearing and see where everybody goes on
12:49 it. I do understand a lot of dirt in
12:52 that area is not good, but I'm not sure
12:54 you violate the um the uh any of the
12:58 Commonwealth's requirements on
13:00 groundwater given I didn't see exactly
13:03 what was contaminating the site. I
13:06 couldn't figure it out. I had to go
13:08 fetch the uh RTNs, look them all up. Um
13:12 I thought most of them were down in the
13:14 lower part of your site, not the upper
13:15 part of your site. So those were just my
13:18 comments.
13:19 Okay. Okay. Thank you. So So Brett, uh
13:23 the RTN's don't uh encompass the entire
13:26 site.
13:27 My understanding and we can follow up
13:30 with WSP as needed. Um but my
13:33 understanding is that you can't have two
13:36 within the same piece of land. So the
13:38 current restriction is on the building
13:40 itself and that um it I don't want to
13:44 talk myself into a corner because I
13:46 don't really know enough about the
13:47 soils. That's why we do have WSB. Um but
13:50 my understanding is that there is one
13:51 within the building itself and but that
13:53 doesn't mean that the soils are not um
13:56 compliant enough for any infiltration
13:58 and we can follow up um separately if
14:02 needed.
14:02 Okay.
14:03 To address that.
14:04 I mean because you can have uh multiple
14:06 RTNS on one site. One can address
14:09 groundwater, one can address soils, one
14:10 can address air. Um so where is WSP? Uh
14:15 were you able to bring an LSP with you
14:16 this evening? I I think that would be
14:18 helpful.
14:21 Uh Chris, any Chris, I don't know if
14:24 you've been
14:25 able to listen in anything from WSP for
14:28 today or were they preoccupied?
14:31 Um
14:34 I know the postal service has contracted
14:36 with them directly. They're a consultant
14:39 to the postal service, not to us. um
14:41 they were uh contacted and um I do
14:46 believe they were provided with this
14:48 meeting request. I can't answer for why
14:50 they're not in attendance.
14:52 Okay, I appreciate that. So um like with
14:55 Commissioner Sullivan, I mean it's not
14:57 up to us to try to parse out the um
15:00 sketch plans and the areas that are
15:02 covered by the AUL. So, uh,
15:05 unfortunately, I think you're headed for
15:07 another continuence here and, uh, you
15:10 have one or two options. Have an LSP
15:12 accompany you next time. Uh, tell your
15:15 client that we really want to talk to
15:16 the LSP or, uh, a much more detailed
15:19 letter, um, addressing the questions
15:22 that, uh, Commissioner Sullivan raised.
15:25 Um, Commissioner Len, what do you have?
15:28 Uh, I don't have any additional
15:29 questions. Thank you.
15:30 Okay. Commissioner Essayazi,
15:32 I I arrived just as it looked like you
15:36 were doing the parking arrangements.
15:38 What I think I was seeing on those was
15:41 that in order to do a single back and
15:43 fill or, you know, one a two-part K turn
15:46 into the spaces, you need the entire
15:48 middle. Um,
15:51 that certainly is efficient. Um, but it
15:54 certainly means you have a lot of black
15:55 top that you're not that you're only
15:58 using for essentially
16:02 reducing from a say a three-point turn
16:04 to a two-point turn. Um, I if that's how
16:08 the post office really feels they have
16:10 to operate,
16:12 you know, from an environmental
16:14 perspective, I'm I'm a little
16:16 disappointed that there's a a little bit
16:18 more uh tradeoff for being able to have
16:22 more imper less impervious coverage and
16:25 um maybe a tiny bit of extra work on the
16:28 part of the drivers. Um, but I'm I'm not
16:31 sure that I feel strongly enough about
16:32 it to say no. Um, but it's it is
16:36 worthwhile thinking a little bit. You've
16:38 shown us a just a few places where
16:40 you're able to do this in one back and
16:42 fill.
16:44 I think I mentioned at the last meeting
16:46 um my office has uh several
16:51 um loading docks for our surrounding
16:54 businesses which back up onto a uh 20
16:57 foot wide street. And they get into
17:00 those spaces all day long every day.
17:04 Okay.
17:05 So, [clears throat] what I can how I can
17:06 respond to that is that this site, as uh
17:10 Brett alluded to, has um non-standard
17:13 parking stalls. The postal service
17:16 requires that these trucks be parked in
17:18 35 ft parking stalls and that they be
17:21 provided with 30 foot turning radiuses
17:26 um and a 60-oot turning circle. And
17:30 currently we have exactly um 60 ft nose
17:34 tonose on the parking stalls and they're
17:36 only 30 ft deep um from and that's a
17:40 deviation from their standard and that
17:43 was something that they uh approved uh
17:46 in order to maximize their their parking
17:48 on this property. But the um the turning
17:51 radiuses they they would not relieve on
17:54 the parking layout. And it's something
17:57 throughout their entire network that
17:59 they have um conservative uh uh space
18:03 requirements for uh not only straight
18:06 trucks but uh tractor trailers and um so
18:10 they require that these sites be
18:13 designed in accordance with their
18:14 criteria and that's what has happened
18:17 here. So, so I guess I would say when
18:19 you're responding to your client
18:22 suggesting that they bring along their
18:23 LSP at a subsequent meeting that you
18:26 might ask them at least for a statement
18:28 that says that they don't think that the
18:30 environmental to standard parking
18:33 arrangements is worth any tradeoff. Um,
18:36 it seems like a bit of a straightforward
18:38 bure bureaucratic answer as opposed to
18:41 environmental review type answer. and
18:44 and I'm pretty sure looking at other
18:46 post offices in the area that um they do
18:50 make exceptions when they want to.
18:53 Okay.
18:54 Thank you.
18:55 Thank you. So, another thing I might
18:57 suggest is I think in one of the um
18:59 slides here you showed vegetation
19:01 surrounding the perimeter. Could we go
19:04 back to that?
19:06 Is that on the post office property?
19:11 Some may be, but it's outside of the
19:13 work limits itself.
19:15 We can look at the drawings to fine-tune
19:18 where the property line actually is, but
19:20 the work limits are actually bound by
19:22 the payment.
19:24 Yeah, understood. Um, but maybe there is
19:28 uh some and think about this. Maybe
19:30 there's a creative solution here where
19:33 you could uh have a more robust uh
19:36 landscaping plan uh or landscaping
19:39 scheme uh in that green area uh that
19:42 we're seeing there. It looks like it's
19:44 it doesn't look like it's um all that
19:47 robust. It looks like there could be
19:48 some improvement there. So, uh
19:50 we'd have to look at the property lines
19:52 on that. I don't believe that is postal
19:55 service property.
19:57 Okay. Well, I I assumed it was because
20:00 you you included it and and pointed it
20:03 out here. Um so, okay. Um well, why
20:07 don't you look into it and see uh what
20:09 the property lines are. Um who the
20:12 adjacent property owner is. Maybe they
20:14 would uh be happy with some uh
20:16 additional landscaping here. Um, but you
20:20 know, throwing that out there because I
20:21 think you're gonna you're going to need
20:23 to come up with uh something a bit more
20:25 creative here. Uh, Commissioner Herpst,
20:28 uh, nothing for me other than looking
20:30 for my fellow commissioner's questions
20:32 to get addressed. Thanks.
20:33 Okay. Thank you. Um, Ellena, uh, I don't
20:36 see any hands raised. Did you get any
20:38 emails?
20:39 Uh, nothing beyond the email that we had
20:41 mentioned at the last hearing related to
20:43 the, uh, lighting choices
20:44 [clears throat]
20:45 at this site. Um but since then no hands
20:48 and no additional emails.
20:50 Okay. Thank you. So with that I'd
20:51 entertain a motion to continue the
20:53 hearing.
20:54 So moved.
20:55 We have a second.
20:56 Second.
20:57 Okay. Commissioner Sullivan.
20:58 I.
20:59 Commissioner Len.
21:04 Commissioner Essarazzi.
21:05 I.
21:06 Commissioner Herpst.
21:07 I.
21:08 I vote I. Commissioner Len. Are you Did
21:11 we lose her?
21:12 Oh, sorry. I You may not have heard me.
21:14 Hi.
21:15 Oh, I'm sorry. Okay. Thank you. That
21:17 carries 5 nothing. Okay. Thank you.
21:20 Um, next item on the agenda is notice of
21:22 intent for D file number 0062156
21:25 from WSP on behalf of H Highleberg
21:29 Materials US Cement LLC for the
21:31 unauthorized pipeline maintenance, peer
21:33 repairs and installation of a new chain
21:35 link fence um security fence at 88 Black
21:38 Falcon Avenue uh South Boston waterfront
21:41 resource areas land subject to coastal
21:43 storm flowage. designated port area 100t
21:45 buffer to coastal bank who's here on
21:47 behalf of the applicant.
21:48 Hi uh hi commission members. My name is
21:50 David Goldstein from WSP and I'll be
21:53 presenting the project.
21:54 Great.
21:56 All right. So um I just want to start
21:59 off again. Thank you very much for
22:00 having us uh for the hearing this
22:02 evening. Um, on the behalf of the
22:05 applicant, H Highleberg Materials US
22:07 Cement LLC, WSP is submitting this after
22:10 the fact notice of intent application to
22:13 the Boston Conservation Commission in
22:15 response to an enforcement order issued
22:17 on on October 7th, 2025 for peer
22:20 repairs, maintenance, and security fence
22:23 installation located at 88 Black Falcon
22:26 Avenue in Boston.
22:28 All subject all work subject to this
22:30 after the fact NOI occurred on Massport
22:33 property under Massport's enabling act.
22:35 Uh Massport is charged with the
22:37 development, operation, and maintenance
22:39 of its properties. As a general rule,
22:41 Massachusetts case law provides that an
22:43 authority or agency of the Commonwealth
22:45 is not subject to municipal bylaws,
22:47 ordinances, or regulations so long as
22:50 the authority or agency is performing an
22:52 essential governmental function and
22:54 there is no specific statutory provision
22:56 to the contrary. Accordingly, as the 88
22:59 Black Falcon Avenue peer repair and
23:01 maintenance improvements project is the
23:02 performance of an essential government
23:04 function by Massport and the Enabling
23:06 Act does not spec specifically require
23:09 Massport to be subject to local wetland
23:11 ordinances, the project filing by
23:13 Massport is not subject to the city of
23:15 Boston's local wetland ordinance and
23:17 related regulations. Uh, this NOI is
23:20 being filed pursuant to the
23:21 Massachusetts Wetlands Protection Act
23:23 and its implementing regulations. So,
23:26 now that I got that out of the way, we
23:27 can go to the next slide. [laughter]
23:30 Sounds like the disclaimer for an
23:32 investment or something.
23:33 Yeah, right. Doesn't it? [clears throat]
23:35 So, uh we'll go over the project
23:37 overview pretty quickly. So, the
23:39 application purpose was to address
23:40 unauthorized peer repairs, maintenance,
23:43 and chain link security fence
23:44 installation uh through this after the
23:47 fact notice of intent.
23:49 Um the enforcement response uh was
23:52 issued by the conservation commission on
23:54 on October 7th, 2025.
23:57 Uh all work again occurred on Massport
23:59 property and uh the completed work uh
24:02 includes pure repairs and maintenance
24:04 along with the installation of a chain
24:05 link security fence. Um and um the local
24:10 ordinance uh we already kind of talked
24:13 about already. So we can continue on to
24:14 the next slide. [clears throat]
24:18 So I'll talk next about the project
24:20 location and site description. So uh
24:23 it's a cement and slag distribution
24:25 terminal at 88 Black Falcon Avenue. Bulk
24:29 vessels deliver materials to the
24:30 northern side of the pier where they are
24:33 transferred to storage silos by a steel
24:35 pipeline. H Highleberg's lease port uh
24:38 lease portion of the pier contains no
24:40 utilities is constructed of timber
24:43 pilings and buffers uh connected to the
24:45 stone concrete and asphalt pier base and
24:48 all work was completed above meanh high
24:51 water and did not extend into previously
24:53 undisturbed resource areas. Next slide.
24:59 So we can go over the resource area
25:00 summary. Um the entire project area is
25:03 within a FEMA zone AE with a base flood
25:06 elevation of 12 feet. We're obviously in
25:09 in a designated port area, the South
25:11 Boston water dependent industrial and
25:13 commercial area supporting marine
25:15 transportation and we're also within a
25:18 100t buffer to coastal bank. There is an
25:21 adjacent coastal bank um that's a
25:23 man-made concrete seaw wall supported on
25:26 steel H piles found underneath the pier.
25:29 And you can see the uh mapping um the
25:32 project locus. Next slide.
25:38 So the project need uh first was
25:40 pipeline maintenance to maintain the
25:42 integrity of the primary cement and slag
25:44 transport line and supports the material
25:47 transfer from bulk discharge vessels to
25:49 the storage silos. Number two is timber
25:52 maintenance. We repaired and replaced
25:54 pierside timbers used as a sacrificial
25:57 buffer and it also helps absorb vessel
25:59 impacts and protect the permanent pier
26:01 structure in dockside operations. And
26:04 finally, the security fence installation
26:07 as requested by the coast guard uh
26:09 creating a safety buffer for employees
26:11 and contractors during unloading events
26:14 and it also enhanced security when ships
26:16 are in port. Um, shallow concrete pads
26:19 brought select areas to grade. Um, as
26:22 part of the climate resilience and
26:24 facility longevity, Boston's waterfront
26:27 is increasingly vulnerable to climate
26:29 change and extreme weather events and
26:31 maintaining critical terminal
26:32 infrastructure helps ensure safe and
26:35 reliable operations during future
26:37 climate related stressors. Right, next
26:39 slide.
26:42 So for the construction activities um it
26:45 included a thousand linear feet of chain
26:47 link security fence. Um along that
26:50 security fence there were nine uh new
26:52 swinging gates. The concrete pad uh that
26:56 was replaced in kind was 1,65 square ft.
27:01 The concrete that was placed was also 32
27:04 cubic yards and seven pipe gaskets were
27:07 replaced. Some additional work uh as
27:10 part of the project included pipeline
27:11 repainting, repainting and maintenance,
27:14 replacement of damaged oak timbers and
27:16 pier bumpers, concrete grading and steel
27:20 plate installation
27:21 and fence post caps and related
27:23 incidental improvements. Next slide.
27:29 Uh so here are some site photographs. Uh
27:31 the photograph on the left shows the uh
27:34 new timber uh as well as the new uh
27:38 concrete that was that was uh installed.
27:42 You can also see in that lefth hand side
27:43 photo a swinging gate. You can see the
27:45 um the little wheel there. So that's one
27:47 of the swinging gates that's part of the
27:49 entire um uh chain link fence structure
27:53 on the right hand side. that is the most
27:57 uh the eastern terminal um of the of the
28:00 chain link fence. And you can see the
28:03 difference between the uh asphalt on the
28:05 left and the new um new cement on the
28:09 right. Um and that extends um almost all
28:14 the way down uh to the west. Next slide,
28:17 please.
28:20 Uh on the left hand side you could see
28:22 uh one of those um steel plating again
28:25 um to grade along the uh the edge there
28:28 of the pier. And on the right hand side
28:31 you could actually see those swinging
28:33 gates in action. Um you know those were
28:36 installed uh specifically um you know
28:38 for access to any sort of barges or um
28:43 other um boats that might be up against
28:46 the pier.
28:48 Next slide.
28:51 So impacts and conformance with
28:53 performance standards. Uh in terms of
28:55 land subject to coastal storm flowage,
28:57 there is no specific WA performance
29:00 standards uh applying to this project.
29:02 Ponding, storm surge, recession and
29:05 flooding are unchanged. Uh for the
29:08 designated port area, there have been no
29:10 effects to water circulation, water
29:12 quality, storm damage prevention, or
29:14 flood control as part of the project.
29:17 And lastly uh for the 100 foot buffer to
29:19 coastal bank there was no work done on
29:22 the seaw wall. There was no effect on
29:24 the wave action, sediment movement, bank
29:26 stability or rare wildlife habitat. All
29:29 of the work was done um on the uh pier
29:32 itself. Next slide.
29:37 Uh so again work was combined to the
29:39 existing developed pier um and resource
29:42 area values and functions were not
29:44 adversely affected. So, uh, the
29:47 applicant respectfully requests approval
29:49 of the completed pure repairs,
29:51 maintenance, and chain linking fence
29:52 security, uh, installation under the
29:55 Massachusetts Wetlands Protection Act.
29:58 Okay. Thank you, David. So, um, the
30:00 questions I have on this, uh, more
30:02 procedural, uh, and Elellena and I, um,
30:05 had a discussed this, uh, earlier today.
30:08 Um the question was um uh actually for
30:13 me it relates to for the certificate of
30:17 completion. Uh do you have a uh stamped
30:21 um
30:22 stamped plan showing the finished
30:25 conditions?
30:27 Yes. Yeah, we do.
30:28 Okay. Was that included in the uh file?
30:30 I'm not sure I saw that. It was. Okay.
30:32 It was. Okay. Uh because I think the
30:35 process here is uh if we um close this
30:39 tonight, it would be issuing an order of
30:40 conditions that you have to record and
30:42 then come back and uh get a COC.
30:45 Okay. I know that's
30:46 actually I'd like to ask about that too
30:48 because I believe um I think I had a
30:51 conversation with Elellena uh this is
30:53 probably a number of weeks ago at this
30:55 point um that she actually I asked the
30:57 question of whether we would need um a
31:00 COC for this project. Um obviously under
31:03 the you know knowledge that this is the
31:06 project's already completed there were
31:08 no impacts to any sort of you know uh
31:12 resource areas or anything like that. Um
31:14 and she had asked the commission whether
31:18 we would need a COC for this and she
31:20 told me that we wouldn't. So I'd just
31:22 like to get a little bit more clarity on
31:24 that.
31:24 Okay. So um maybe there was some
31:26 miscommunication. Elena what's um
31:29 I can speak to that. David I apologize.
31:31 I um so I think when we had chatted
31:32 about that I had said that it would
31:34 depend on what the commission was
31:35 looking for for the project and when
31:37 Chair Parker and I had touched base
31:38 about this earlier today. Um the thing
31:41 that we were sort of stuck on here is
31:43 that um from a procedural standpoint uh
31:46 the state requires orders of conditions
31:48 to be recorded um so that they're
31:50 present on the deed. Uh, so I know that
31:52 when you and I had talked about this, I
31:54 I wasn't sure whether it was going to be
31:57 based on a question of whether the
31:58 commission needed additional information
32:00 or if there was additional monitoring,
32:02 things like that that would need to
32:03 happen. Um, but it does come down to the
32:05 administrative piece.
32:07 Sure. Okay. All right. No, that makes
32:08 sense to me. Thank you.
32:10 Yeah. I mean, I think when the order of
32:11 conditions is issued, it says right on
32:13 there it has to be um recorded within, I
32:15 don't know, 15 days, maybe 30 days. Um
32:18 and then Elena, you bring up um the
32:20 other point about uh monitoring. Um I'll
32:23 let you take that.
32:25 Absolutely. Yeah. So, uh just given the
32:28 nature of the work that was done and the
32:29 fact that it wasn't originally um
32:31 permitted in any capacity, one of the
32:33 things that uh we had discussed I
32:35 believe on the site visit was also um
32:37 the question of whether there could be
32:38 some sort of report that is sent to
32:40 commission staff for um the number of
32:43 years that the commission thinks is
32:45 appropriate. um just documenting the
32:47 conditions, ensuring that the work that
32:49 was conducted is is sort of structurally
32:51 stable um isn't experiencing any sort of
32:54 deterioration. Um so I think that that
32:56 would be something that we would
32:57 recommend including in the uh set of
32:59 conditions and I would defer to the
33:01 commission on how frequently we were
33:02 thinking perhaps twice a year um photos
33:05 and you know a written narrative
33:06 submitted to commission staff just to
33:08 ensure that everything is um staying in
33:10 place.
33:11 Sure. Yeah. And uh and to that um I
33:14 would ask um if um H Highleberg the the
33:17 client would be able to uh do that
33:20 inspection themselves.
33:23 I think so. I I mean I think if
33:25 somebody's conducting the inspection and
33:27 has concerns about something that might
33:30 be happening under the deck um other you
33:32 know more structural issues that are
33:33 coming up that would be something that
33:35 we maybe want a second opinion on. But
33:37 for the um I think that if we decide on
33:40 specific locations that are photographed
33:42 um and the specific criteria that we'd
33:43 be looking for in the report um that's
33:45 something that I think H Highleberg
33:47 would be able to provide.
33:48 Okay. Yeah. No, that we're we're
33:50 amendable to that to that.
33:52 Okay, that sounds good. And um I think I
33:55 would phrase this a consultation
33:57 regarding the structural integrity uh
33:59 and conditions of the um of the pier
34:05 as opposed to a report ele um as far as
34:08 a report I think um it's it's it's going
34:10 to be hard for you to nail down exactly
34:12 which portions or which uh you know uh
34:15 yeah portions of the pier or the the
34:17 work site um that you um you know that
34:21 you want. Um, and it might make sense to
34:25 leave it open to if and you have the
34:28 ability to do this anyways. You can
34:30 always go and inspect, but um you might
34:32 want to at least the first time take a
34:34 walk and um to see the site yourself.
34:37 Sounds great.
34:38 Yeah.
34:39 Well, maybe plan to do that um I'm
34:42 thinking late winter, early spring, just
34:45 to see how it's fared through the, you
34:46 know, the worst of that weather.
34:48 Yeah, makes sense. Okay. Uh,
34:50 Commissioner Sullivan.
34:52 Yeah. Um, was there an engineer of
34:54 record that did a design for this work
34:56 or do they just decide to do it on their
34:58 own?
34:59 Um, I'm going to actually
35:02 ask um the client here, Michael, if he
35:06 could um to speak to that.
35:08 Yeah. Good evening. Uh, Michael
35:10 Martunis. I'm the environmental and
35:12 safety manager for the H Highleberg
35:14 Boston terminal. Uh this work was done
35:16 as needed. Uh as the timbers were
35:20 damaged, uh they were replaced as the
35:22 pipeline needed uh maintenance. It was
35:24 repaired. There was not an engineered
35:27 planned project for this work.
35:32 And and I assume this is Massport uh
35:35 land. Uh the the landlord, is that
35:38 correct?
35:38 That is correct. Yes.
35:40 Yeah. And do you guys have to tell
35:42 Massport when you're doing stuff just
35:44 that they're here? They're here before
35:45 us like every other hour and uh it just
35:48 seems very strange that you're within
35:50 five feet of water and it didn't seem
35:52 like you had to do anything. It just I
35:54 just curious how that came about.
35:58 Um as to whether or not we told Massport
36:02 we were doing the repairs.
36:04 Yeah. I mean you're apparently you're
36:05 required to do it even though they own
36:07 the land. You you required to keep the
36:09 repairs, keep it in good shape.
36:12 Yeah.
36:12 Uh yes. Uh I I see Juan Carlos is is on
36:16 the call. Perhaps you can speak to the
36:18 communication.
36:19 Yeah, I'm here. Can you hear me?
36:21 Yes.
36:22 Yeah. So, yes, they are uh Mr. Sullivan,
36:25 they are they are obligated to notify
36:27 Massport of this kind of work. In this
36:29 particular instance, they did not.
36:31 Okay. Yeah, [clears throat] that's all I
36:34 was asking. I just wondering how this
36:36 all happened. That's all.
36:37 Yeah. And I don't mean to break in, but
36:38 Ellena, I think that um this was a
36:41 situation I think the general counsel
36:43 for the company um addressed us uh last
36:47 year. It was I mean it felt like it was
36:49 just yesterday, but it was a while ago.
36:51 Um is this a situation where um H
36:55 Highleberg bought the facility or bought
36:58 the operations?
36:59 That was one of the
37:01 Yeah, they inherited this. Yeah,
37:02 that yeah, that was one of the
37:04 complicating factors here is um that
37:05 this had originally come up when
37:07 commission staff were conducting a site
37:08 visit at the terminal with Massport. Um
37:12 and nobody on the site visit knew that
37:14 this work had occurred. Um and then
37:17 after that work had been completed, uh
37:20 the company changed hands and so H
37:22 Highleberg is is sort of um yeah filing
37:25 this after the fact NOI uh not having
37:27 necessarily been the the entity that
37:30 conducted the work in the first place.
37:32 Yeah, this work was completed under
37:34 Coastal Cement and H Highleberg
37:36 Materials purchased uh Coastal's parent
37:38 company on April 1st of 2025.
37:42 So, they're they're new new to this
37:44 site.
37:46 New, but they've inherited the
37:48 liability.
37:49 Exactly.
37:51 Commissioner Sullivan.
37:52 Yeah. No, if it's any consolation, the
37:54 work looks like it's done
37:55 professionally, so that's a plus.
37:58 Okay. Thank you, Commissioner Len.
38:02 I had a question, and this might be more
38:04 for Ellena, about um [clears throat] in
38:06 the photos there's one of of a diesel uh
38:09 tank, and I was curious if that's
38:11 considered part of the project, and if
38:13 there's anything in the order of
38:15 conditions um addressing that, or
38:17 I think the the rest of this um isn't
38:20 under an existing order. Um it I I think
38:23 that this this part of the seapport uh
38:25 because of all of the different port
38:26 functions tends to kind of
38:30 go about the work differently. Um not to
38:32 say that it wasn't permitted, but I
38:33 think that it's just been there for for
38:35 quite a while.
38:37 Thank you. That's all.
38:38 Thank you, Commissioner Essayazi.
38:41 Nothing on this. Thank you.
38:43 Thank you, Commissioner Herpst.
38:46 Nothing for me either. Thank you. Okay.
38:48 Thank you, Elena. Uh any hands raised?
38:51 I see no hands and nothing in our inbox
38:55 either or nothing in the chat.
38:56 Okay. So with that, I would entertain a
38:58 motion to close the hearing and issue an
39:00 order conditions with a special
39:01 condition that by annually there be a
39:05 consultation with commission staff to uh
39:09 inspect the integrity of the uh work.
39:14 So moved.
39:15 You have a second.
39:18 Second. Thank you, Commissioner
39:20 Sullivan.
39:21 Hi,
39:22 Commissioner Len.
39:23 Hi,
39:23 Commissioner Essayazi.
39:25 Hi,
39:26 Commissioner Herpst.
39:27 Hi.
39:28 And I vote I that carries for uh 5
39:30 nothing. Thank you.
39:32 Thank you very much.
39:33 You're welcome. Okay, next item on the
39:35 agenda. And I think uh uh Commissioner
39:38 Len um you have something to say to us.
39:40 I'll uh recuse myself from this one.
39:43 Thank you.
39:43 Okay. Thank you. Okay. Uh, notice of
39:46 intent for DP fall number 0062155 in
39:49 Boston, file number 2026-047
39:52 from Weston and Samson Engineers on
39:53 behalf of the Boston Parks and
39:55 Recreation Department for the temporary
39:57 repair and stabilization of the masonary
39:59 arch openings at Jamaica Pond Boat House
40:02 507 Jamaica Way, Jamaica Plane. Uh,
40:04 resource areas um bordering land subject
40:07 to flooding, inland bank, land
40:10 underwaterway, 25- ft waterfront area,
40:12 and 100 ft buffer to bank. Who's here on
40:15 behalf of the proponent?
40:17 Alex Gaspar, Weston and Samson.
40:19 Uh Brandon Conungle, Weston and Samson.
40:24 And I do believe uh Kevin Bogle is
40:27 Yeah. Kevin Bogle from Boston Parks
40:29 Department.
40:30 Yeah, he's trying to hide back there.
40:32 Fair enough. Kevin a lot. Yeah. Okay. Um
40:35 floor is all yours.
40:36 Great. Thank you.
40:39 Yep. So, we already sort of opened it
40:41 up, but we have submitted a notice of
40:43 intent for the temporary structural
40:45 support system that we're proposing at
40:47 Jamaica Pond Boat House. Next slide.
40:52 Again, we've sort of already gone over
40:54 our project team, but Alex Gaspar here
40:56 from Weston and Samson um sort of
40:58 heading the environmental permitting. We
41:00 have Brandon Conungle as our project
41:02 manager, and then Kevin Bogle from
41:05 Boston Parks Center Recreation.
41:09 Just sort of to get everyone oriented,
41:12 we are at 507 Jamaica Way. I have sort
41:14 of outlined in a red box um where
41:17 exactly we are working. This is on the
41:19 east side of Jamaica Pond and we are
41:22 working right under this portion of the
41:24 structure um on the arches below the
41:26 structure. I think from there I'll turn
41:29 it over to Brandon to do some background
41:32 and then run you through the project.
41:34 Great. Thanks so much. Next slide.
41:36 So, uh, the building is, uh, uh, very
41:40 well aged. Uh, constructed in 1913. It's
41:43 a brickmasonry structure. Um, about, uh,
41:48 we'll say 7 to 8 years ago. I'm thinking
41:52 of my math. 2019,
41:54 uh, Boston Parks asked us to go out and,
41:58 uh, evaluate the, uh, structural
42:01 integrity of these peers.
42:03 had been noticed that there was some
42:05 cracking and some separation. The mortar
42:08 joints were getting larger. So, we've
42:10 been actually monitoring this uh since
42:12 2019. Uh we are seeing some increased uh
42:16 separation in the joints and uh slippage
42:19 of the bricks themselves. As you can see
42:21 in the photo to the left, uh we've
42:24 actually uh highly encouraged, strongly
42:26 recommended that the building not be
42:29 occupied. Uh but uh we do understand
42:32 there is a larger project uh coming in
42:35 the pipeline about five years out.
42:37 They're looking to do some significant
42:39 renovations to the building. But in the
42:42 interim, we don't want to continue to
42:44 see the building uh um sacrifices
42:47 sacrifice it structural integrity. So,
42:50 this is really a uh 0 to 5year interim
42:54 uh repair uh in order to keep the
42:57 building from uh falling or uh
43:00 continuing to um uh fall in disrepair uh
43:04 specifically from a structural
43:06 perspective. Next slide.
43:10 As you can see in these uh photos uh the
43:13 significant cracking. There are some
43:15 wood braces in uh one of the arches. Uh
43:18 but there are three arches uh that are
43:21 showing significant cracking
43:22 particularly at the corner. You can see
43:24 in the lower left uh you can see um uh
43:29 also in the lower right some uh
43:32 significant separation breakage slippage
43:34 of the uh brick column itself.
43:37 Next slide.
43:42 So our proposed uh scope is to install
43:45 three temporary structural steel shoring
43:49 u arches uh within the uh the brick
43:53 arches themselves. Uh the intent is uh
43:57 that again we're looking at a zero to
43:59 fiveyear band-aid while the rest of the
44:02 building is uh uh going underneath
44:05 architectural design and you know major
44:09 repairs uh in about a 5-year window. Um
44:13 but we are trying to keep this as
44:15 localized in order to keep uh one the
44:18 overall impacts uh minimal and uh
44:21 prevent further degradation of the
44:23 structural foundations.
44:25 Um noting that uh part of the challenge
44:29 or the issue uh where the uh brick uh
44:34 switches over to a concrete foundation.
44:36 We did note that there is uh some uh rip
44:40 wrap uh or lack of rip wrap, we should
44:43 say, some deterioration of the actual uh
44:47 sediment or the the pond bottom where
44:50 the building meets the pond. Um so we'd
44:54 like to prevent uh further erosion uh of
44:58 that by installing some rip wrap around
45:01 the base of the columns. um and and
45:05 what's happening is the the columns the
45:07 brick or the concrete is being uh
45:10 undermined by the um uh soil erosion. So
45:14 we're trying to prevent that. Next
45:16 slide.
45:20 Uh so we completely expect to uh access
45:24 the area by land even though the corner
45:27 itself is right at the W's edge. Uh we
45:30 met uh the wonderful folks from the
45:33 concom out there uh last week and uh
45:37 they were able to actually get down and
45:39 walk along uh the edge where the
45:41 building meets the pond and the pond
45:43 meets the building. Uh while it is damp,
45:46 it is uh walkable. We don't expect that
45:49 there will be any work done from the
45:51 water. Um but depending on when the
45:55 actual work happens uh whether you know
45:58 snow melt or rainstorms whatever there
46:01 is slight minimal changes in the water
46:04 elevation. Uh we are prepared to include
46:07 sandbags and potentially dewatering
46:10 while this work happens. Uh very
46:13 localized. Um but we expect that you
46:16 know at most they may need to use a
46:19 small excavator to um go over a railing
46:24 uh to provide you know to put these
46:26 steel members in place uh just due to
46:29 the weight. There is about a 3 to 4 foot
46:32 grade braid change uh between the
46:35 retaining wall that uh meets the
46:37 building and at the pond edge. Uh so
46:41 there may be some temporary whether it's
46:43 a ladder uh or some sort of ramp device
46:46 that uh may be needed for the actual uh
46:50 work to be accessed. Uh but we don't
46:53 actually expect any uh major equipment
46:56 to be down at the pond bottom where the
47:00 uh building meets the pond bottom. So uh
47:03 again it's only three arches. Um, we
47:06 expect that there may be some on-site
47:08 fabrication, some off-site fabrication,
47:11 but conservatively we're giving
47:12 ourselves uh five weeks to do this work.
47:16 Uh, we expect it should take less, but
47:19 uh, you know, weather uh, conditions may
47:22 impact it. Um, the expectation is we uh,
47:26 achieve this permit. Um we'd like to
47:30 finalize any of the plans uh go out to
47:33 bid uh early or December, early January
47:37 so that this work can be done uh March
47:40 uh April and have the building secured
47:44 uh tight tightened up before the spring
47:47 uh programming occurs. Next slide.
47:53 Uh so you can see here a plan uh the you
47:57 know the sandbags if needed uh
48:00 conservatively we're assuming we're
48:01 going to need them but uh just keeping
48:04 the work area dry uh as needed. Um the
48:08 three columns uh are in the lower right
48:11 of the the plan, the building plan
48:13 itself,
48:15 but [clears throat] uh noting that the
48:16 water at the at the time we were out
48:19 there last, the water is sitting a
48:21 little low, but it's within five 5T of
48:25 the building edge. So, next slide.
48:34 Next. I don't know. There we go. Uh just
48:36 a context plan. Uh again, we expect all
48:40 the staging to occur upland out out of
48:43 the water. Uh there's a as I noted about
48:46 a 3 to 4 foot granite block boulder
48:50 retaining wall. This would be uh the
48:53 staging area would be at the top of the
48:55 the wall within the pave existing pave
48:58 sidewalk area, coned off, fenced off for
49:01 public safety purposes. Um, you know, we
49:05 expect it to be very minimal. Just um
49:07 some steel members, maybe some uh
49:10 fabrication equipment or equipment to
49:12 actually um maneuver the the bracing
49:16 into place. Um we're not necessarily
49:19 showing uh the limits of whether it's a
49:22 ladder or a ramp uh depending on the
49:25 contractor and how they choose to access
49:28 the actual work area. Um, but we would
49:31 work with them to ensure, you know, if
49:33 it's a a 4 foot wide by 10 foot long
49:37 ramp, you know, we're assuming a worst
49:39 case scenario for temporary impacts. Uh,
49:42 but uh, in speaking with the engineers,
49:46 uh, we believe most of this will be able
49:48 to be hand uh, maneuvered. Uh so maybe
49:52 you know the contractor just for their
49:54 own cost benefits might just use a
49:56 ladder but uh without having got a
50:00 contractor under scope yet we don't know
50:02 exactly how they anticipate to the the
50:04 work area itself. So um we're trying to
50:08 be a little bit flexible on the means
50:09 and methods. Next slide.
50:11 Okay. Brandon, can you just hold on for
50:12 one second? You bet. Uh Commissioner
50:14 Essargi, how are you doing for time?
50:16 I'm I'm fine.
50:18 Okay. Okay. Thank you, Brandon. Sorry
50:20 for the
50:20 Yeah, no problem.
50:21 Y
50:22 my difficulty was on the earlier end,
50:24 not the later end.
50:25 Oh, okay.
50:27 Uh here's a couple of section details or
50:29 elevation details showing uh the columns
50:34 um where the cracking is. We will be
50:35 doing mortar repairs um to uh help with
50:41 the uh uh decrease of further
50:44 degradation. But uh the major work
50:47 occurring uh with this implementation of
50:50 these steel arches uh as noted in the
50:53 lower uh left detail. um and and
50:57 installing the rip wrap to uh prevent
51:00 further degradation of where the
51:03 concrete meets the pond bottom. Next
51:06 slide.
51:10 And I'm going to hand it back to uh Alex
51:13 to work through all
51:16 impacts.
51:18 Thank you. Yep. So the site was
51:20 delineated. We flagged the annual high
51:23 water in the field which you will see as
51:25 the orange line. Um it does sort of
51:28 become a dashed estimated line under the
51:30 boat house just because we were not able
51:32 to really access underneath the boat
51:34 house at the time of the delineation.
51:36 But um that line does go all the way up
51:39 under the under the boat house. And then
51:42 we just have our associated buffers with
51:45 that which is the 25 ft waterfront area
51:48 in that dashed blue and then the 100 ft
51:51 buffer zone in the dashed yellow.
52:00 Additionally, this does fall within a
52:03 FEMA zone A. So we do have some impacts
52:05 to that resource area as well. um there
52:09 are there is not a elevation associated
52:12 with the zone A. So we have sort of
52:14 overlaid it onto our plans to the best
52:16 of our ability um and estimated those
52:18 impacts
52:26 just our anticipated environmental
52:29 impacts. So, as mentioned at the
52:31 beginning of this presentation, we are
52:33 anticipating impacts to land underwater,
52:35 bordering land subject to flooding bank,
52:38 the 25- ft waterfront area. Um, it looks
52:41 like it got a little skewed, but um the
52:44 100 foot buffer as well, and we can talk
52:47 through those on the next slide.
52:51 So, our temporary impacts, as Brandon
52:54 mentioned, there is the possibility of
52:55 some water control being needed. So we
52:57 had proposed sandbags and a turbidity
52:59 curtain um with some possible dewatering
53:03 if needed. So we those are our temporary
53:06 impacts. We also have that material
53:08 layown area that we showed on the plans
53:10 that is occurring in our buffer zone. So
53:12 that is resulting in some temporary
53:14 impact to the buffer zone as well as
53:17 access. Access will also be part of our
53:20 temporary impacts for the permanent
53:22 impacts. that's really going to come
53:24 from the placement of the rip wrap and
53:26 concrete. Sort of the meat of the
53:28 project will be the permanent impact.
53:31 But overall,
53:33 the majority of our impacts are
53:35 temporary in nature and mostly from
53:37 controlling the area during
53:39 construction. Overall, the permanent
53:41 impacts are are fairly minimal. And we
53:44 see this project as being necessary to
53:47 prevent any impact to public safety as
53:50 well as the wetland resource areas that
53:52 exist underneath the boat house.
53:55 I believe that is it. So we would love
53:58 to open it up to any questions or
54:00 comments.
54:01 Great. Thank you, Alex. Okay. So quick
54:03 question from me. I guess I have two.
54:05 One is uh marine habitat. I see you're
54:08 using you may be using turbidity um
54:11 curtains. um any issues there?
54:15 We don't anticipate
54:17 there being any issues there. Um as
54:20 Brandon mentioned, I mean, the area is
54:21 fairly dry at the moment, so we aren't
54:24 anticipating having to impact much
54:26 habitat and it's o it's mostly made up
54:30 of rocks and sort of cobble there. So,
54:33 we didn't um note any habitat at the
54:35 time. So, I don't believe that that
54:38 temporary control would would result in
54:41 in any impact to marine habitat.
54:44 Okay. Um, and Brandon, you mentioned uh
54:47 ladder or a ramp. Uh, I know that we're
54:50 interested in um uh your construction
54:53 method there. I assume you're not going
54:54 to know that until you bid this out. So,
54:58 uh, I'd be looking for a special
54:59 condition that, u um, preconstruction
55:03 that, um, staff has provided with more
55:05 information on the means and methods
55:07 there.
55:08 Absolutely. Uh, and that would have been
55:10 our recommendation, uh, prior to closing
55:13 this out anyway. So, you know, we want
55:15 to make sure we're all on the same page
55:18 uh, and that, you know, it's safe, but
55:21 also practical and not overdone or
55:24 underdone. So,
55:25 great. I appreciate that. Elena, what do
55:27 you have?
55:28 Uh, that was it.
55:30 That was it. Okay.
55:31 That condition. Sorry to clarify.
55:33 [laughter]
55:33 Thank you.
55:34 Other than I think you, Hussea, and DD
55:36 deserve hazard pay that look like uh
55:39 maybe a little dangerous place. I I hope
55:41 you don't do things like that uh
55:43 frequently. You're an amazing team. We
55:45 don't want to lose you.
55:47 That that the building looks like it is
55:50 ready to fall down. Um, Commissioner
55:53 Sullivan,
55:54 Brandon, you mentioned a small excavator
55:56 that's going to be um on the upland pot
55:59 and lowering the steel in or is it going
56:01 to be lowered into the where the water
56:04 would be area?
56:06 No, [snorts] I mean so at least in the
56:07 current conditions as we are today um
56:10 it's more for just ease of you know
56:14 handling the material.
56:15 Yeah. Uh the actual arches themselves
56:17 are uh just at the precipice where the
56:21 water meets the building. So it is
56:23 technically walkable, dryable, but just
56:26 for you know we wanted to make sure we
56:28 were conservative on sort of a worst
56:30 case scenario.
56:32 So you're you're doing something
56:35 temporary. Why aren't because it's only
56:37 involving three arches. Why aren't we
56:40 permanently rebuilding the foundation
56:42 now and getting it ready for the big big
56:46 five-year rehab later and then you're
56:48 all done?
56:49 I would uh defer to Kevin on that one.
56:52 Yeah. Yeah. So, I think it's uh it's
56:55 partially a cash flow issue. So, the
56:58 larger renovation will be a larger pot
57:00 of money. Um and we will be able to do
57:03 all of the work at one time. uh at that
57:05 point. Um this work although we have
57:09 been tracking it for eight years, it's
57:11 kind of very recently been a oh we can't
57:14 wait for the master plan redoing of the
57:16 building. We need to kind of step in in
57:19 an emergency uh state and kind of get
57:22 this support up as we continue to
57:24 develop the larger plan for the building
57:27 itself which is not just for this
57:29 building. It's this building. there is
57:31 an adjacent um gazebo uh they call it a
57:35 band shell and a plaza area between so
57:38 it's it's quite a large process um that
57:41 these columns would be a part of.
57:44 Yeah. Yeah. No, I know I I actually had
57:47 seen this several years. I turned it in
57:49 two commissioners ago.
57:51 Okay.
57:52 And and said somebody better watch it
57:54 because this thing's going to slide and
57:56 slip.
57:56 And here we are. So this is this is a
57:59 steel reinforced so you don't worry
58:00 about the wood and if if it if you slip
58:03 it and it goes nine years you're you're
58:05 sure that the building won't go down.
58:06 That's basically what you're doing.
58:09 Correct.
58:10 And you know the idea of the water you
58:12 can control the level of that water over
58:14 by Perkins Street.
58:15 Yeah, we're aware. Um, I mean, I think
58:18 once we get a contractor under, uh, a,
58:22 you know, on board and with a schedule,
58:24 I think, uh, we'll work with Boston
58:26 Parks and
58:28 to adjust the elevation accordingly if
58:31 needed.
58:32 Yeah. Well, it it would make sense
58:34 rather than try to sandbag the thing.
58:36 Yep.
58:36 You know, even rain runoff, you can you
58:38 can drop it in a couple of days when you
58:40 know a big storm's coming. So,
58:42 Right.
58:43 That's that's all I had.
58:45 So, that's interesting. Now,
58:46 Commissioner Sullivan, um, you can, uh,
58:48 regulate the water level. Where does the
58:50 water go when you drain?
58:51 It drops down to the Wards pond lever
58:54 pond down to the Muddy River.
58:55 Oh, interesting. Okay. Thank you.
58:58 Uh, Commissioner Estari,
59:00 another thing I had the same question
59:01 that Commissioner Sullivan had, which is
59:04 why temporary, but uh, Kevin's answer
59:06 makes sense.
59:08 Okay. Thank you, Commissioner Herps.
59:11 Nothing for me. Thanks.
59:12 Okay. Um, Elena, I don't see any hands
59:16 raised. Did you get any emails, texts,
59:18 or otherwise?
59:19 Uh, no, nothing like that. The only
59:21 other thing I I think is that uh we
59:23 would like to be notified if the
59:25 strategy ends up being that the water
59:27 level is going to be um altered to
59:29 conduct the work. So, we would just want
59:30 to be aware of that before it happens.
59:32 Of course.
59:32 Okay. Yep. Okay. Great. So, with that, I
59:35 would uh entertain a motion to close a
59:37 hearing and issue an order of conditions
59:38 with special conditions that once the uh
59:42 uh preconstruction before work starts uh
59:46 um the applicant will provide the uh
59:48 well, you'd be providing the
59:50 construction plans anyway. Um but um
59:53 spotlighting whether you're using a lamp
59:55 and a yeah, lamp, [laughter] a lamp and
59:58 a rer uh a ramp and a ladder. Um uh and
1:00:02 also um notified if the water level is
1:00:07 um decreased to permit work.
1:00:12 So moved.
1:00:14 Do we have a second?
1:00:15 Second.
1:00:17 Commissioner Sullivan
1:00:18 I.
1:00:19 Commissioner Essari.
1:00:20 Hi.
1:00:21 Commissioner Herpst
1:00:23 I.
1:00:24 And I vote I that carries four nothing.
1:00:25 Okay. Thank you. Good luck. Be careful.
1:00:29 We'll do. Thank you all so very much.
1:00:31 Okay, we're now going to be begin our
1:00:33 regular meeting. Uh, first item on the
1:00:35 agenda is a request for a certificate of
1:00:37 compliance for Boston file number
1:00:39 2024-008
1:00:41 from the city of Boston Environment
1:00:42 Department for restoration activities
1:00:44 within Matah Hunts property located in
1:00:47 multiple parcels off of Itasa Street and
1:00:50 uh, Conan Street or Cananan Street in
1:00:53 Matapan. uh resource areas, isolated
1:00:56 vegetated wetlands, and 100 ft buffer to
1:00:58 IVW.
1:01:00 Thank you. Yes. So, uh this is of course
1:01:03 a familiar site to everyone on the
1:01:04 commission. Um staff conducted a site
1:01:06 visit in April of this year, uh but
1:01:09 because there were still some plantings
1:01:10 that were establishing, uh the urban
1:01:13 wilds team suggested that the various um
1:01:16 erosion controls were kept in until
1:01:18 those plants were more established. uh
1:01:20 everything has now been removed. So the
1:01:22 the project site is clear of all of that
1:01:24 in jurisdictional areas. Um and based on
1:01:27 that we are uh recommending that the
1:01:29 commission issue a complete certificate
1:01:31 of compliance. Uh there are a few
1:01:33 perpetual maintenance conditions which
1:01:35 we've noted and we also drafted some
1:01:37 additional maintenance conditions which
1:01:39 we think would be appropriate to allow
1:01:42 the urban wilds team to continue
1:01:43 managing uh invasive species and other
1:01:46 uh nuisance plant species within the
1:01:48 buffer zone. Uh there are uh let's see
1:01:52 it is eight of them total and uh they
1:01:55 specify the requirements for anybody
1:01:57 conducting the work. It would be uh
1:01:59 either conducted by urban wild staff or
1:02:01 supervised by urban wild staff and it
1:02:04 would be limited to the type of work
1:02:05 that was already permitted under this
1:02:07 order of conditions.
1:02:09 Okay, good. Anticipated my question.
1:02:12 Okay, which uh perpetual maintenance
1:02:14 conditions are going to be left standing
1:02:16 here?
1:02:16 Yes. So, those are going to be numbers
1:02:18 58
1:02:19 Mhm.
1:02:20 65
1:02:21 Mhm.
1:02:22 77,
1:02:24 83,
1:02:25 84,
1:02:27 94, and 95.
1:02:30 Okay. Thank you. Um, any questions from
1:02:33 any commissioners?
1:02:34 How big is this Urban Wild staff?
1:02:38 Uh, how big is the staff?
1:02:39 Yeah,
1:02:40 they uh recently lost a few of their
1:02:42 members. Um, Dee, can you remind me? Are
1:02:45 they down to five people?
1:02:53 Sorry. Um, let's see. I don't think I
1:02:57 know the exact number, but five sounds
1:02:58 about right.
1:02:59 Yeah. No, I'm just curious if it's like
1:03:01 25 people.
1:03:04 Okay, that's all.
1:03:06 But they um they do have a partnership
1:03:08 with Power Core. So um part of the plan
1:03:11 for this site is uh some of it would be
1:03:13 happening within the 100 foot buffer but
1:03:15 most of it would be happening in
1:03:16 non-jurisdictional areas uh that they
1:03:18 would be working with power core to
1:03:19 train them on the type of work that
1:03:21 would need to happen at Matahun anyway.
1:03:25 Okay. I think that's an increase. I
1:03:28 remember when we did a cleanup I thought
1:03:30 uh at that point it was only uh I
1:03:32 thought they only had like one employee
1:03:34 um uh he was over in Allenale. It went
1:03:38 up and then it went way down.
1:03:40 Yeah. And then Nick came on. Nick Long.
1:03:42 Um I always thought it was just the two
1:03:44 of them. But anyway, um
1:03:46 No, that's just that's just to get you
1:03:48 to work. That's all that is, Mr. Chair.
1:03:50 Yeah, exactly.
1:03:51 They had five people. You'd go back
1:03:52 home.
1:03:53 They're sandbagging us. Yeah, exactly.
1:03:55 Any other questions on Matter Hotwoods?
1:04:00 Okay. So with that, I would um entertain
1:04:04 a motion to issue a certificate of
1:04:06 compliance for Boston file number
1:04:09 2024-008
1:04:12 uh with the perpetual maintenance
1:04:14 conditions 586577
1:04:17 83 84 94 and 95.
1:04:20 So moved. Do
1:04:21 we have a second?
1:04:24 Second.
1:04:26 Thank you. Commissioner Sullivan. Hi.
1:04:29 Commissioner Esarazzi. I,
1:04:31 Commissioner Herps.
1:04:32 I,
1:04:33 and I vote I. That carries for nothing.
1:04:35 Um, quick question, Elena. Why, uh, was
1:04:39 this work not covered under the, um,
1:04:41 local ordinance? I know it's a
1:04:43 jurisdictional issue. I'm just curious.
1:04:45 Uh, so it's local only, just not state.
1:04:47 So the state doesn't recognize
1:04:50 vegetated wetlands.
1:04:51 Got it. I miss I was misreading it
1:04:53 because D file number is always first
1:04:55 for some reason in my head. It's Boston
1:04:57 file number. Okay. Sorry.
1:04:59 Okay. Dumb question. Okay, next item.
1:05:01 Uh, request for a certificate of
1:05:03 compliance for D file number 0061762
1:05:07 in Boston file number 2021-00003
1:05:10 from KO Engineers and Scientists on
1:05:12 behalf of the Massachusetts Department
1:05:14 of Conservation Recreation for pool and
1:05:17 parking lot renovations located at 75
1:05:20 and 95 Turtle Pond Parkway and Hyde
1:05:22 Park. uh resource areas, riverfront
1:05:25 area, waterfront area, 100 foot buffer
1:05:26 to inland bank, 100 foot buffer to BVW,
1:05:29 and 100 foot buffer to IBW.
1:05:32 Thank you. Yes. So, uh similarly, staff
1:05:35 actually conducted a site visit on the
1:05:36 exact same day as Mata Hunt, uh April
1:05:38 16th, 2026. Uh at at that point, there
1:05:41 were a few things that still needed to
1:05:43 be done. Uh namely, putting in fish
1:05:45 plates, some signage, and all of that
1:05:47 has now been taken care of. So, the work
1:05:49 is complete. Uh based on that, we would
1:05:52 recommend that the commission issue a
1:05:54 complete certificate of compliance and
1:05:56 the perpetual maintenance conditions are
1:05:58 numbers 27, 45, 51, and 68.
1:06:03 Okay. Any questions?
1:06:07 No.
1:06:07 Okay. So with that, I would entertain a
1:06:10 motion to issue a certificate of
1:06:11 compliance for D file number 0061
1:06:14 1762 in Boston file number 2021-00003
1:06:19 with the perpetual maintenance
1:06:20 conditions 27451
1:06:22 and 68.
1:06:24 So moved. You
1:06:25 have a second.
1:06:26 Thank you. Commissioner Sullivan
1:06:28 I.
1:06:29 Commissioner Len
1:06:31 I.
1:06:31 Commissioner Essayazi.
1:06:33 I.
1:06:34 Commissioner Herpst.
1:06:35 I. And I vote I that carries 5 nothing.
1:06:38 Okay. Continued as a request for
1:06:40 certificate of compliance for D file
1:06:42 number 0061963
1:06:44 and Boston file number 2023-053.
1:06:47 Also continued uh request for a
1:06:49 certificate of compliance for D file
1:06:52 0061816
1:06:54 and Boston file number 2021-042.
1:06:57 Uh and uh next item is a request for a
1:07:00 certificate of compliance for D file
1:07:03 0061830 in Boston file number 2021-054
1:07:07 from Hancock Associates on behalf of 59
1:07:10 Gov Street LLC or Gove Street LLC for
1:07:14 the construction of a 4-unit residential
1:07:16 dwelling located at 59 GV Street in East
1:07:18 Boston resource area land subject to
1:07:21 coastal storm uh flowage. Elellanena.
1:07:24 Yes. Uh so we had conducted a site visit
1:07:26 on October 15th and uh there were a few
1:07:30 remaining items uh namely that there was
1:07:32 a discrepancy between what was shown in
1:07:34 the asbuilt and what was on observed on
1:07:36 site as far as storm water infiltration.
1:07:38 Uh they have since fixed that and um
1:07:41 based on that we would be recommending a
1:07:43 complete certificate of compliance to be
1:07:45 issued. Um, we did also want to note
1:07:48 that originally the plan for this site
1:07:50 was for the um building to be the units
1:07:53 were going to be sold. Um, but that has
1:07:55 now pivoted and they are going to be
1:07:56 rentals instead. So, as far as any
1:07:59 language included in the deed, we don't
1:08:00 need to um I guess originally the order
1:08:04 of conditions I think had identified
1:08:05 language that was based on these being
1:08:08 uh units that would be sold to new
1:08:09 owners and that's no longer the case. Um
1:08:11 but the perpetual maintenance conditions
1:08:13 that we would recommend are numbers 44,
1:08:16 46, 52, and 65.
1:08:21 Okay. Any questions from anyone?
1:08:24 Hearing none, I would entertain a motion
1:08:26 to issue a certificate of compliance for
1:08:28 D file number 0061830 and Boston file
1:08:30 number 2021-054
1:08:32 with the perpetual maintenance
1:08:34 conditions numbers 44, 46, 52, and 65.
1:08:39 So moved. We have a second.
1:08:41 Second.
1:08:42 Thank you. Commissioner Sullivan.
1:08:43 I.
1:08:44 Commissioner Len.
1:08:45 I.
1:08:46 Commissioner Essarialazi.
1:08:47 I.
1:08:48 Commissioner Herps.
1:08:49 I. And
1:08:50 I vote I. Carries. Five. Nothing. Okay.
1:08:51 Elena, the floor is yours.
1:08:53 Administrative updates.
1:08:54 Uh, yes. Taking feedback that we have
1:08:57 gotten recently into account. I will
1:08:58 simply be informing the commission of
1:09:00 administrative approvals that we have
1:09:01 issued and not asking permission.
1:09:04 [laughter] So, please speak now. Um, or
1:09:06 I suppose forever hold your peace. Uh so
1:09:09 the first one is for a sculpture
1:09:11 installation at L Prey Park in East
1:09:13 Boston. We issued an administrative
1:09:15 approval for the installation of the
1:09:17 sculpture. It is within Oh, and DDD,
1:09:19 sorry. We have slides for these if you
1:09:20 want to go to the next one. Um debuting
1:09:23 new slides. Thank you, Husseina. Uh so L
1:09:26 prei park sculpture installation. It's
1:09:27 made up of three separate components. It
1:09:29 will be installed for approximately a
1:09:31 period of 6 months. And uh again, it'll
1:09:33 be within LCSF 100 foot buffer to
1:09:35 coastal bank and 25 ft waterfront. Uh
1:09:38 it's a relatively minimal impact within
1:09:40 these areas of approximately 30 square
1:09:42 ft and considering the entire area is
1:09:44 already paved um and this would not be
1:09:46 impacting permeability, we thought this
1:09:47 was appropriate for an administrative
1:09:49 approval.
1:09:51 Fantastic. Any questions?
1:09:53 Is it a sculpture that some of us could
1:09:55 understand what it means or is it a
1:09:56 total abstract?
1:09:58 I mean sculptures are historically very
1:10:02 literal, easily inter. know I I think
1:10:04 that it will probably be uh a very
1:10:06 experiential sculpture. So um I think
1:10:09 the idea behind this is actually that um
1:10:11 people are going to be able to step up
1:10:12 onto one of the plinths uh to experience
1:10:14 it from a certain uh sort of a certain
1:10:17 perspective and people will also um
1:10:19 they've incorporated a more accessible
1:10:21 portion of the the setup as well. Um so
1:10:24 yeah, I would recommend checking it out
1:10:25 once it's been installed.
1:10:27 Well, you can send me a picture. Yeah, I
1:10:29 was I was just wondering on this is this
1:10:31 a permanent that's it. They put it there
1:10:34 and it lasts 10 years.
1:10:35 So, it'll be it'll be in for about I
1:10:37 believe it's about 6 months. It's at
1:10:38 least it's less than a year and I can
1:10:40 confirm that timeline. Um but it's it's
1:10:42 only for a temporary period
1:10:44 and they've also been in close
1:10:45 coordination uh with parks since this
1:10:48 will be on parks property
1:10:50 and then do they put another one next
1:10:52 year or
1:10:54 uh curious we've had Yeah. So, we've had
1:10:56 interest in this site before. Um, I
1:10:58 think actually the the last time that
1:11:00 somebody had reached out about
1:11:01 installing a sculpture, they were
1:11:02 proposing it in Low Prey, but they were
1:11:04 proposing it in an area that wasn't
1:11:06 already paved, which brought up some
1:11:07 more significant permitting
1:11:09 requirements. And so, they ended up
1:11:10 picking a different site in Boston.
1:11:12 Um, but this one, since it's already in
1:11:13 this paved uh portion of the park, we
1:11:16 thought that this was, you know, a more
1:11:17 appropriate um admin approval situation.
1:11:19 Yeah.
1:11:21 So, there might be more in the future.
1:11:24 Can't wait.
1:11:25 Great. Um, and I did just look up what a
1:11:27 plinth is if you need to know.
1:11:32 Any other questions?
1:11:35 Okay, Elena.
1:11:37 Excellent. Um, slightly less up to
1:11:39 interpretation. Uh, DCR is proposing
1:11:42 some uh ADA compliant fixes to three
1:11:45 sidewalk ramps on Park Drive. Uh, these
1:11:48 are close to the muddy river and, uh,
1:11:50 they would be within the 100 foot buffer
1:11:51 to inland bank and 25 ft uh, waterfront
1:11:54 area. So, uh, they would just be
1:11:57 removing these panels which are
1:11:58 approximately 8 by 12 ft. Uh, they would
1:12:00 be then disposed of off, uh, offsite and
1:12:03 the new ones would be put in on top of a
1:12:05 gravel base, uh, so that the grade
1:12:07 matches and the work is approximately
1:12:09 going to take 2 days. Uh, there are
1:12:11 three of these locations in total.
1:12:13 They're all located within this uh,
1:12:15 screenshot that we have included on the
1:12:16 slide.
1:12:18 Okay, any questions?
1:12:23 Next up, you were busy.
1:12:25 Yes. Um,
1:12:25 we're giving away the story here.
1:12:27 I know. [laughter]
1:12:29 Um, so, uh, this is not an approval of
1:12:31 any sorts, but we just want to inform
1:12:33 the commission. Um, Commissioner Estie
1:12:35 Smartassi, you probably already know
1:12:36 this, but, uh, the MW has informed us
1:12:39 that the annual, uh, Chestnut Hill
1:12:41 Reservoir winter drawdown has started.
1:12:43 Uh, it's taking place currently. So, it
1:12:45 started on November 1st and it will be
1:12:47 going to December 1st. Um this is
1:12:49 something that uh MW has been informing
1:12:52 the commission of since 2015 I believe.
1:12:54 Uh and the purpose of the draw down is
1:12:57 to manage invasive plant species. So the
1:12:59 idea is to allow for the exposed plants
1:13:02 and their roots to freeze. Um and it's a
1:13:05 sort of lighter touch u approach to
1:13:08 invasives management at the site.
1:13:14 Is that is that cruel and unusual
1:13:16 punishment for plants? reason
1:13:18 Commissioner Estee Smartasi. [laughter]
1:13:20 Any comments?
1:13:21 Better than poison, I guess.
1:13:23 Yeah,
1:13:23 it is. And mil foil.
1:13:26 Yeah.
1:13:28 Not less so than herbicide, I guess.
1:13:32 Okay.
1:13:32 And desiccating uh means drying out or
1:13:35 by removing moisture,
1:13:38 potentially causing the roots to die. Is
1:13:40 it successful?
1:13:42 Um most years. It it depends on how cold
1:13:45 it gets. So, um, we've had years where
1:13:48 we it's just been too warm and we end up
1:13:50 refilling without having achieved much.
1:13:52 Um, but, uh, probably two out of three
1:13:56 years we get a significant [snorts]
1:13:58 dieback. We're doing this on several
1:13:59 other reser bigger reservoirs, um, to
1:14:02 the west in the Sbury area. It's been
1:14:05 pretty successful here. Here it's all
1:14:07 rip wrap around the edge and it's really
1:14:10 difficult other than applying draining
1:14:12 the reservoir and applying an herbicide.
1:14:14 It's really difficult to get out the
1:14:15 plants. So, if you get a good freeze,
1:14:18 you really knock them back pretty far.
1:14:20 Okay. Crossing my fingers.
1:14:22 And this will drain to the Muddy River,
1:14:23 too, eventually.
1:14:25 Yeah.
1:14:26 I've been curious about the timeline,
1:14:28 too, considering it was what, 75 degrees
1:14:30 today. So, fingers crossed for more
1:14:33 seasonal weather.
1:14:35 Okay. Um, actually, if the weather stays
1:14:37 like this, maybe you'll burn them off,
1:14:39 right?
1:14:39 Honestly. [laughter]
1:14:41 Um, okay. Uh Elena, what else?
1:14:44 Yes, next up is in fact another
1:14:45 administrative approval. Uh this one is
1:14:47 in Hyde Park, 1530 River Street. Um so
1:14:50 you can see here the work that is
1:14:52 proposed um is within the 100 foot
1:14:55 buffer to the Naponet River. Uh it's an
1:14:57 area that is already completely paved uh
1:14:59 and otherwise developed. So um the
1:15:02 project proponents are proposing to pour
1:15:04 a concrete pad and install a diesel
1:15:06 generator. Uh this will result in 36 ft
1:15:09 of impacts within the 100 foot buffer.
1:15:11 And uh the reason that we thought this
1:15:13 would be appropriate for an
1:15:14 administrative approval is that the
1:15:16 permeability wouldn't be changed on site
1:15:18 because the area is already completely
1:15:19 paved. Uh no materials will be stored on
1:15:22 site and the generator will be installed
1:15:24 once the concrete pad has been poured.
1:15:26 They're expecting uh work to take about
1:15:28 a week and the special conditions that
1:15:30 we include in the administrative
1:15:31 approval include spill management.
1:15:34 Is there a se separate diesel fuel tank
1:15:36 for this thing or is it just the tank
1:15:38 contained in the generator?
1:15:40 That I don't know, but I can ask.
1:15:43 Yeah, because they would have to have a
1:15:45 spill containment
1:15:46 on the if they have a tank.
1:15:49 You'd want to make sure they got a spill
1:15:51 containment that can take the entire
1:15:52 tank.
1:15:53 Excellent. We'll we'll check with them
1:15:55 and depending on their response, uh
1:15:56 we'll make sure that we get that on
1:15:58 file. Yeah,
1:16:00 I don't think they can install it
1:16:01 without containment, but I mean I guess
1:16:04 it depends the size of the generator.
1:16:06 Yeah,
1:16:07 right. Yeah,
1:16:09 interesting. Good question.
1:16:10 Um, yeah. Uh, do you have any others?
1:16:13 Last item actually uh is something that
1:16:15 we are requesting action on from the
1:16:17 commission. So, uh the Boston Harbor
1:16:19 Shipyard and Marina in East Boston uh
1:16:22 reached out to us because a portion of
1:16:24 the seaw wall had collapsed. Um you can
1:16:27 see it in this photo. So, this is taken
1:16:29 um sort of it's a view under the deck.
1:16:32 Uh there was a 15 ft section of the seaw
1:16:34 wall which collapsed and that resulted
1:16:35 in a large piece of concrete leaning up
1:16:37 against one of the piles. So, that's
1:16:39 sort of contributing to this um issue of
1:16:42 the pile becoming structurally unsound.
1:16:44 While we were out there, you could also
1:16:46 really see uh the waves and tidal action
1:16:48 going into this area that is not
1:16:50 supposed to have water in it and uh
1:16:52 pulling more of this fill out. So, um,
1:16:55 based on this, we we thought that an
1:16:56 emergency certification would be
1:16:58 appropriate. Uh, Massport did declare a
1:17:00 public health andor safety emergency for
1:17:02 this because of the potential for the
1:17:04 area to become further destabilized. Uh,
1:17:07 and we issued an emergency certification
1:17:09 on Monday, uh, November 2nd. So, repairs
1:17:13 began yesterday. They're anticipated to
1:17:15 take one week. Um, the way that they're
1:17:17 going about this is that they're
1:17:18 removing the pieces of the seaw wall
1:17:20 that they're able to, and then they are
1:17:21 placing rip wrap along the seawward
1:17:23 slope. uh and they already know that
1:17:24 they will be coming back to the
1:17:26 commission with a notice of intent in
1:17:27 the spring um to conduct additional
1:17:30 repairs for the site, but right now
1:17:32 their priority is uh stabilizing the
1:17:34 site ahead of the winter.
1:17:36 Please tell me Oh, apologies. Yep.
1:17:39 Yeah. No, go ahead.
1:17:40 Uh we to clarify would be requesting
1:17:42 that the commission um ratify the
1:17:44 emergency certification if they find it
1:17:46 appropriate.
1:17:47 Okay. Please don't tell me the three of
1:17:48 you were anywhere near this picture.
1:17:51 Just on top of it. [laughter]
1:17:52 Yeah. just on top of it.
1:17:55 There are people working on boats. They
1:17:56 seemed very unbothered.
1:17:58 Okay. [laughter]
1:17:59 Uh any questions from anyone?
1:18:01 I I do. Um so the filing said referenced
1:18:06 a plan, but the plan was not a plan. It
1:18:08 was like a picture of the site. Um
1:18:10 yes. So they what they were using for
1:18:13 that um is that the the site has their
1:18:15 sort of um repairs and maintenance order
1:18:18 of conditions which was issued I think
1:18:19 in maybe late 2024. Um, and so they were
1:18:23 using that for the delineations, which I
1:18:25 think is why they probably refer to it
1:18:27 as a plan.
1:18:28 Yeah. But I guess what I'm saying is we
1:18:30 don't have a plan. We, you know, they
1:18:31 talk about a new revetment and it
1:18:33 doesn't show and it talks about it not
1:18:35 being in contact with the water, which
1:18:38 was hard to picture. So,
1:18:40 um
1:18:42 I I think we need an actual I mean I
1:18:44 know they they've started so maybe we
1:18:45 need an as built but um we don't really
1:18:48 have anything that tells us what it is
1:18:51 they're doing and they're doing it right
1:18:53 at the W's edge so that doesn't feel
1:18:55 great to me. Um
1:18:56 and I guess yeah, this did raise sort of
1:18:58 an administrative question on our end.
1:19:00 Um when we were sort of talking through
1:19:02 the requirements for the emergency
1:19:04 certification, uh one of the things that
1:19:06 we were sort of going back and forth on
1:19:08 was the amount of documentation,
1:19:11 especially when it comes to stamp plans,
1:19:12 of what to require for an emergency
1:19:14 certification since the state requires
1:19:17 us to at least respond within 24 hours
1:19:19 of getting that notice. So, I didn't
1:19:20 know if um starting to include a
1:19:23 requirement of asbuilts as a standard
1:19:25 condition of the ESERT or um
1:19:27 Commissioner Herbs, if you have
1:19:28 recommendations on sort of what we could
1:19:31 ask for that would allow for the work to
1:19:34 or allow, I guess, for the materials to
1:19:36 come to us in a timely enough manner to
1:19:38 deal with the emergency situation while
1:19:39 still getting us the information that we
1:19:41 would need.
1:19:42 Well, I guess I'm assuming if they're
1:19:43 dealing with it in an emergency, they
1:19:45 they had a plan. They know what they're
1:19:47 going to do. Um, so they should have
1:19:50 been able to show you that. Um, even if
1:19:52 it I I know Commissioner Sullivan always
1:19:56 insists on stamp plans, but I mean I
1:19:58 would have taken a sketch or something
1:20:00 that I mean we just we don't know what
1:20:03 this is or at least I don't. I can't
1:20:04 picture it. Maybe you have a better
1:20:06 picture of it, but I I feel like they
1:20:08 have to know what they're doing. Um, and
1:20:11 so they should be able to tell you like
1:20:13 what size stone, where's it going, that
1:20:15 kind of thing. Um,
1:20:16 Got it. Excellent. So what I will do is
1:20:18 for this I'll go ahead and reach out to
1:20:21 uh the consultant and ask for at least
1:20:23 sketches at this point in time and then
1:20:26 um include maybe in the ratified
1:20:28 emergency certification a requirement
1:20:29 for an asbelt once they've completed the
1:20:31 work and then we can also incorporate
1:20:32 those requirements into future eerts
1:20:34 that we that we might issue.
1:20:37 Yeah, if that makes sense to the
1:20:38 commissioners. I mean I think um
1:20:42 definitely at this point we should at
1:20:44 least get an ass build and and yeah even
1:20:46 a sketch now they
1:20:49 yeah it's a great point and I think
1:20:51 we've had an issue with um this
1:20:53 particular um entity before about uh
1:20:57 after the fact nois and not having an
1:20:59 asbuilt. So
1:21:00 I remember the sinkhole was the the most
1:21:02 recent issue with that where yeah
1:21:04 it was difficult for us to get an
1:21:06 asbuilt uh that somebody would stamp
1:21:09 So, did I did I read it right that
1:21:12 they're saying they're putting in a
1:21:13 revetment, but it's not gonna
1:21:15 I mean, they don't talk about being in
1:21:17 any water-based resource area. I I just
1:21:21 couldn't understand it. Um
1:21:23 I was So, when we originally got the
1:21:25 call, I was hesitant about whether this
1:21:27 would even be an emergency certification
1:21:29 based on the description. And then when
1:21:31 we got there and understood that there
1:21:33 was now water essentially where there
1:21:35 shouldn't be, [laughter] that was I
1:21:38 think what um drove it home for us. And
1:21:40 I'm um I'm just going to pull up any
1:21:43 additional photos that I might have. So
1:21:44 I mean I think they talked about a
1:21:46 siltation curtain. I should know. I just
1:21:47 looked at this. But um anyway, I just
1:21:52 for the future I I feel like this this
1:21:55 went even as an emergency. They we need
1:21:58 a little more than what we got.
1:22:00 Got it. Absolutely.
1:22:02 Okay. Thank you. So, Elena, you know
1:22:06 what to put in the letter.
1:22:07 Yes, absolutely. And um before they
1:22:11 complete work, I'll make sure that we
1:22:12 have some sort of visual for um and
1:22:14 further details on Yeah. the the methods
1:22:18 that they're actually going to be
1:22:19 utilizing.
1:22:20 Okay.
1:22:20 Okay. Thank you.
1:22:21 Commissioner Herps, do you want to
1:22:22 review the letter?
1:22:24 Uh
1:22:26 I'm I don't feel like I have to. I just
1:22:28 Yeah. Thank you.
1:22:30 Sure. Uh any other questions?
1:22:35 Okay. So with that, I would entertain a
1:22:37 motion to uh ratify the emergency
1:22:40 certification
1:22:41 for um the Boston Harbor Shipyard
1:22:44 Marina, 256 Margin General Street in
1:22:46 East Boston, uh regarding the collapsed
1:22:50 seaw wall with the um with the condition
1:22:53 that Elellena uh will be putting in the
1:22:57 um uh the emergency letter um a request
1:23:02 for uh at least a sketch of the work
1:23:06 that's being done now and will be
1:23:08 requiring an asbuilt completion of work.
1:23:14 So moved.
1:23:15 Thank you. Do we have a second?
1:23:17 Second.
1:23:19 Okay. Commissioner Sullivan.
1:23:20 I.
1:23:21 Commissioner Len.
1:23:22 I.
1:23:23 Commissioner Essa Sargi.
1:23:24 I.
1:23:25 Commissioner Herpst.
1:23:26 I.
1:23:27 And I vote I. So that carries five
1:23:28 nothing. Ellen, anything else?
1:23:32 That's it for admin updates. That's all.
1:23:35 You're very busy. You are all very busy.
1:23:37 Thank you for all your work. Okay. Um,
1:23:40 acceptance of meeting minutes. Uh, as
1:23:42 usual, they were done. Uh, very well.
1:23:44 Which leads me to ask, are you having
1:23:46 Claude do the minutes?
1:23:48 Never. Never. Never.
1:23:49 No. Okay. Okay. Let's see what's going
1:23:52 on here. I saw an M dash in a place.
1:23:56 I will. The hill for me to die on is M
1:23:58 dashes and semicolons. And I really hate
1:24:00 that AI is [laughter] taking that away
1:24:02 from me.
1:24:04 Okay.
1:24:05 Okay. So, with that, um, I looked them
1:24:08 over. They look great. Uh, entertain a
1:24:10 motion to accept the meeting minutes
1:24:11 from October 7th, 2026 and October 21st,
1:24:14 2026.
1:24:16 So moved.
1:24:17 Do we have a second?
1:24:19 Second.
1:24:20 Okay. Commissioner Sullivan,
1:24:21 I.
1:24:22 Commissioner Len,
1:24:23 I.
1:24:24 Commissioner Essa Sargi,
1:24:26 I.
1:24:27 Commissioner Herpst,
1:24:28 I.
1:24:29 And I vote I. Okay. Uh, time to adjourn.
1:24:32 We have one more meeting before
1:24:33 Thanksgiving, right? We do. Okay. So, I
1:24:36 guess we'll see you in a few weeks.
1:24:37 Thank you everyone.
1:24:39 Thanks.
1:24:39 Have a good evening.